Keysbrook Mineral Sands Project

 
Client
 

Keysbrook Leucoxene Pty Limited

Forecast Completion Date
 

December 2015

Location
 

WCP Site – Keysbrook WA
MSP Site – Picton WA

Project Manager
 

Peter Parsons

Scope of Work
 

GR Engineering was engaged to undertake the engineering design, procurement construction and commissioning of a wet concentrator plant (WCP) and associated infrastructure for the Keysbrook Minerals Sands Project. The WCP featured overland pumping, thickening and tailings storage infrastructure and had a design throughput of 4.5mtpa to produce circa 119ktpa of HMC. The HMC was processed further at the Doral Mineral Separation Plant (MSP) to produce approximately 68ktpa of leucoxene and 28ktpa of zircon concentrate for export.

The WCP utilised conventional wet gravity separation to produce a valuable Heavy Mineral Concentrate (HMC). The WCP received feed slurry from a Mining Field Unit (MFU) through a dedicated pipeline. Fine material was removed from the feed slurry by hydrcyclones and the “slimes” fraction were delivered to a storage void for dewatering and rehabilitation. Coarse tailings from the WCP were also delivered to the mining void for dewatering and subsequent rehabilitation. HMC produced by the concentration of the feed material was stored and dewatered on the site before being trucked to the MSP for further refining.

The existing Doral MSP was modified and upgraded to enable the Keysbrook HMC to be processed at a rate of 113ktpa on a month on month off campaign basis. Upon completion, the notional production from the Doral MSP upgrade was 31ktpa of L70 leucoxene, 37ktpa of L88 leucoxene and 28ktpa of zircon concentrate for export.

Associated News
 

Keysbrook Mineral Sands Project.Posted 19-Nov-18.
Commencement of Keysbrook Mineral Sands Project. Posted 04-Mar-14. 
Notice of Preferred Contractor - Keysbrook Mineral Sands Project. Posted 28-Oct-13.